Let the games begin!
At 7:50 am I heard noises that let me know heavy machinery had arrived at our house and the stones started coming soon after that.. Here we go!
They were supposed to start at Don and Amy's but it didn't work out that way -- Not a good thing for us unfortunately.
We watched the work on Don and Amy’s property throughout the day and I sent Don updates periodically. I was really surprised that he wasn’t
at home today to oversee the work but I guess it turned out ok.
| 10:30am - second load just delivered |
| 1:45pm -- large stone delivered |
| 2:24 -- that's it for today |
Our project was not quite so compact. Justin went off the reservation a bit and changed the plan. Dave was good with it and he promised to "stretch" the stone as much as he could. We have over 200 feet of shoreline to protect!
By 10am the gazebo had been moved and we were on to chopping down trees. Yes, we had to chop down two trees to allow the dump trucks better access. The closer the rocks could be dumped to the shore, the fewer loads (and less time) it would take to get the stones placed in the water.
Tilt up just enough to roll pipes under.
Then tilt up from the other side -- then roll.
Very carefully and very slowly!
|
| Distance from deck to gazebo -- about five inches. |